Report for the Edinburgh Tram Inquiry
classification
💱 q-fin.GN
keywords
riskedinburghreporttrammanagementassessmentcostinquiry
read the original abstract
This report reviews the Edinburgh tram project's risk management. Projects frequently overrun their cost and timelines and fall short on intended benefits. Cost, schedule, and benefit risk of projects need to be carefully considered to avoid this. The report describes and evaluates risk assessment and management for the Edinburgh tram. The report was produced as part of the Edinburgh Tram Inquiry. Keywords: risk assessment, risk management, infrastructure, megaprojects, optimism bias, strategic misrepresentation, planning fallacy, behavioral science.
This paper has not been read by Pith yet.
discussion (0)
Sign in with ORCID, Apple, or X to comment. Anyone can read and Pith papers without signing in.